    A Technique to Shorten the Duration of a Project to Meet
Solved

A Technique to Shorten the Duration of a Project to Meet

Question 54

Question 54

Multiple Choice

A technique to shorten the duration of a project to meet the target dates best describes


A) project enhancement.
B) fast tracking.
C) thought process mapping.
D) quantitative project assessment.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q49: Advantages of PERT include<br>A)inexpensive to maintain.<br>B)flexibility.<br>C)easy to

Q50: Which of the following was developed by

Q51: In CCPM,a finite amount of time that

Q52: Free float is an early warning and

Q53: The shortest time an activity can be

Q55: Which of the following demands extensive hardware,is

Q56: Before any successor activity can be initiated

Q57: The earliest finish time is the total

Q58: PDM uses time as a common factor

Q59: When working with project management software,factors that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines