Multiple Choice
Which of the following project audit report questions addresses PMBOK's integration management knowledge area?
A) Do value-related processes exist?
B) Do scope-related processes exist?
C) Do schedule-related processes exist?
D) Are budget variances part of the project budget review?
Correct Answer:

Verified
Correct Answer:
Verified