Multiple Choice
Which of the following project audit report questions addresses PMBOK's communication management knowledge area?
A) Are quality metrics developed,measured,and monitored?
B) Are minutes of meetings stored and distributed?
C) Is the project team being recognized and rewarded?
D) Does the project plan consist of a contingency plan?
Correct Answer:

Verified
Correct Answer:
Verified