Multiple Choice
The _____ is the most pessimistic outcome of a task.
A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) dominant-case estimate (D)
Correct Answer:

Verified
Correct Answer:
Verified