In Project Schedule Management, Which Process Generates the Main Outputs

Question 29

Multiple Choice

 In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?


A) sequencing activities
B) defining activities
C) resource estimating activities
D) estimating activity durations