  5. Question
    Which Term Is Used for a Significant Event on a Project
Solved

Which Term Is Used for a Significant Event on a Project

Question 25

Question 25

Multiple Choice

 Which term is used for a significant event on a project that normally has no duration?


A) milestone
B) activity attribute
C) activity sequence
D) schedule baseline

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q20:  In an AOA network diagram, what occurs

Q21:  After defining project activities, the next step

Q22:  The critical path on a project can

Q23:  Which is one of the main outputs

Q24:  Network diagrams are the preferred technique for

Q26:  In a(n) _ relationship, the "from" activity

Q27:  Which technique involves network diagramming and is used primarily

Q28:  In project schedule management, what is the

Q29:  In project schedule management, which process generates

Q30:  The technique of fast tracking can result

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines