 Which type of dependencies are inherent in the nature of work being performed on a project?


A) mandatory
B) discretionary
C) external
D) random

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q55:  The arrows in a network diagram represent

Q56:  In project schedule management, the main goal of which

Q57:  In project schedule management, which process primarily

Q58:  A drawback of the project management software

Q59:  What term is used for the amount

Q61:  What is the Theory of Constraints? Describe

Q62:  Duration estimates can be provided as a

Q63:  During which relationship is the "from" activity unable

Q64:  Where would a draft schedule for a

Q65:  Which technique is used for making cost and schedule

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines