Multiple Choice
Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?
A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers
Correct Answer:

Verified
Correct Answer:
Verified