Multiple Choice
Which is true of a finish-to-finish dependency?
A) It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started.
B) It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start.
C) It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
D) It is a dependency in which the "from" activity must start before the "to" activity can be finished.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: Which is a similarity between the crashing and
Q50: _ states that if something can go
Q51: Which dependencies do AOA network diagrams use?<br>A)
Q52: One of the first reality checks on
Q53: _ have no duration and no resources
Q55: The arrows in a network diagram represent
Q56: In project schedule management, the main goal of which
Q57: In project schedule management, which process primarily
Q58: A drawback of the project management software
Q59: What term is used for the amount