Which is a similarity between the crashing and fast tracking?
A) both spread out tasks over a long period of time to ensure the quality of work is maintained
B) both invariably result in increases in total project costs
C) both can shorten the time needed to finish a project
D) both are network diagramming techniques used primarily to predict total project duration