After Working with Key Stakeholders to Define Activities and Calculate

Question 39

Multiple Choice

 After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?


A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.