Multiple Choice
Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting?
A) budgetary
B) definitive
C) rough order of magnitude
D) analogous
Correct Answer:

Verified
Correct Answer:
Verified