Multiple Choice
The main outputs of which process are a quality management plan, quality metrics, project management plan updates, and project documents updates?
A) controlling quality
B) planning quality management
C) quality certification
D) performing quality assurance
Correct Answer:

Verified
Correct Answer:
Verified
Q57: _ diagrams trace complaints about quality problems
Q58: Customer requirements are an important aspect of
Q59: Which term is used when the project's
Q60: Which statement is one of Juran's ten
Q61: The International Organization for Standardization (ISO) defines
Q63: Which testing involves an independent test performed
Q64: DeMarco and Lister's study on organizations and
Q65: The term _ means a product can
Q66: Which five-phase improvement process do projects that
Q67: Six Sigma's target for perfection is the