O'Conner Corporation Purchased Land with a Building on It

Question 59

Multiple Choice

O'Conner Corporation purchased land with a building on it.It removed the old building and constructed a new one.Which of the following costs would not be included in the cost of the building?


A) constructing the new building
B) removing the old building
C) building permits
D) foundation
E) all would be included