Multiple Choice
Which of the following correctly pairs a technique with its approach?
A) The program evaluation and review technique (PERT) uses probabilistic estimation to determine the duration of an activity.
B) The critical path method (CPM) uses subjective estimation to determine the duration of an activity.
C) The program evaluation and review technique (PERT) uses optimistic estimation to determine the duration of an activity.
D) The critical path method (CPM) uses pessimistic estimation to determine the duration of an activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q36: Which of the following is a limitation
Q37: Which is the critical path in the
Q38: If the delivery of goods or services
Q39: Which of the following is not a
Q40: Which of the following is not a
Q42: The Gantt Chart _.<br>A)links project activities to
Q43: One way to determine the duration of
Q44: Which of the following is NOT included
Q45: Which of the following statements about the
Q46: Documenting the risk is helpful as a