Multiple Choice
Which is the critical path in the following?
A) Path 1 takes 18 days.
B) Path 2 takes 14 days.
C) Path 3 takes 22 days.
D) Path 4 takes 16 day.
Correct Answer:

Verified
Correct Answer:
Verified