Multiple Choice
At a merge point,______.
A) the largest preceding EF becomes the ES for that node
B) the largest preceding ES becomes the EF for that node
C) the smallest preceding EF becomes the ES for that node
D) the smallest preceding ES becomes the EF for that node
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q75: Which of the following statements is true
Q76: Which of the following is NOT a
Q77: A pure-project structure is characterized by _.<br>A)a
Q78: The debate about "jobs versus the environment"
Q79: A project begins with _.<br>A)an appraisal of
Q81: A project life cycle is useful because
Q82: Early start time (ES)refers to _.<br>A)the earliest
Q83: Which of the following is the final
Q84: Which of the following is NOT a
Q85: The cancellation of many energy projects was