Which of the following is NOT a question a company is likely to ask in assessing project risk?
A) What adverse events are likely to happen?
B) What are the possible outcomes of these adverse events?
C) Who will be held responsible in case of project failure?
D) How can the potential risk be identified?
Correct Answer:

Verified
Correct Answer:
Verified