Multiple Choice
The output of individual production quantities of the end items to be produced at various points of the short-term planning horizon is called ______.
A) available-to-promise (ATP) inventory
B) the master production schedule (MPS)
C) sales and operations planning
D) rough-cut capacity planning
Correct Answer:

Verified
Correct Answer:
Verified
Q77: The process of scheduling receipt of inventories,raw
Q78: The output of the master schedule is
Q79: Which file provides information on machine capacity,machine
Q80: The master schedule reflects demand from _.<br>A)final
Q81: Parent Item A requires two units of
Q83: An MRP system works best in _.<br>A)a
Q84: To facilitate production,it is necessary to _.<br>A)aggregate
Q85: A JIT system works best in _.<br>A)a
Q86: A standard quantity issued to the production
Q87: The effectiveness of a master schedule depends