Multiple Choice
A JIT system works best in ______.
A) a pull system
B) a push system
C) a constant demand system
D) a constant supply system
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q80: The master schedule reflects demand from _.<br>A)final
Q81: Parent Item A requires two units of
Q82: The output of individual production quantities of
Q83: An MRP system works best in _.<br>A)a
Q84: To facilitate production,it is necessary to _.<br>A)aggregate
Q86: A standard quantity issued to the production
Q87: The effectiveness of a master schedule depends
Q88: The time between placing an order and
Q89: The leftover inventory from previous periods that
Q90: The process of updating the master schedule