Multiple Choice
A scheduling process used to determine in advance the capacity required at each work center for each time period to complete the jobs by the due dates by beginning with the due date for each job and loading the processing requirements for these jobs at each work center by proceeding backward in time is called ______
A) current-date scheduling
B) forward scheduling
C) due-dates scheduling
D) backward scheduling
Correct Answer: