Solved

The Makespan for the Jobs Listed in the Table Below

Question 58

Multiple Choice

The makespan for the jobs listed in the table below under the shortest processing time (SPT) rule is ______.  Job  Processing time  (in days}  Due date (in days from  to day’s date}  A 49 B 1018 C 66 D 1219 E 717\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing time } \\\text { (in days\} }\end{array} & \begin{array} { c } \text { Due date (in days from } \\\text { to day's date\} }\end{array} \\\hline \text { A } & 4 & 9 \\\hline \text { B } & 10 & 18 \\\hline \text { C } & 6 & 6 \\\hline \text { D } & 12 & 19 \\\hline \text { E } & 7 & 17 \\\hline\end{array}


A) 39
B) 40
C) 38
D) 37

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge