Multiple Choice
______ are simple decision rules that are used to select jobs for the next operation in order to control the flow of work as jobs progress through a single process,machine,or work center.
A) Scheduling rules
B) Sequencing rules
C) Priority rules
D) Job processing rules
Correct Answer:

Verified
Correct Answer:
Verified