Multiple Choice
For sequencing N jobs through two machines,processes,or work centers in the same order,_________ provides the most efficient method.
A) priority rules
B) Johnson's rule
C) batch rule
D) process rule
Correct Answer:

Verified
Correct Answer:
Verified