The average flow time for jobs listed in the following table under the earliest due date (EDD) rule is ______.  Job  Processing time (in  days)   Due date {in days from  to day’s date}  A 59 B 1118 C 36 D 1219 E 1017\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing time (in } \\\text { days) }\end{array} & \begin{array} { c } \text { Due date \{in days from } \\\text { to day's date\} }\end{array} \\\hline \text { A } & 5 & 9 \\\hline \text { B } & 11 & 18 \\\hline \text { C } & 3 & 6 \\\hline \text { D } & 12 & 19 \\\hline \text { E } & 10 & 17 \\\hline\end{array}


A) 17.8 days
B) 19.8 days
C) 20.8 days
D) 18.8 days