Multiple Choice
Charts must be updated periodically to reflect new job arrivals and revised time estimate.This statement is a limitation of ______.
A) assignment method
B) control charts
C) Gantt load charts
D) Gantt sequence charts
Correct Answer:

Verified
Correct Answer:
Verified