Which of the Following Metrics Is Used to Calculate the Cumulative

Question 40

Multiple Choice

Which of the following metrics is used to calculate the cumulative or total time required to complete a given number of repetitions of a task or produce a given number of unit of an item?


A) unit time coefficient value
B) flow time coefficient value
C) production time coefficient value
D) total time coefficient value

Correct Answer:

verifed

Verified