Multiple Choice
Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 19 iterations before the process reached a steady state of 33 hours.If Weston has a 94% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.
A) 42.92 hours
B) 44.80 hours
C) 41.21 hours
D) 42.11 hours
Correct Answer:

Verified