Multiple Choice
In calculating the time-cost trade-off combinations for a project's crash options,the slope for each activity is given by ______.
A) the ratio of the (crash cost less normal cost) to (normal time less crash time)
B) the ratio of the (normal time less crash time) to (crash cost less normal cost)
C) the product of the (crash cost less normal cost) and (normal time less crash time)
D) the sum of (crash cost less normal cost) and (normal time less crash time)
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The time-phased budget _.<br>A)identifies the correct sequencing
Q17: A project's baseline represents _.<br>A)our best understanding
Q18: If the most optimistic time for completing
Q19: Find the area under the normal curve
Q20: The formula for the expected duration of
Q22: If project completion times are normally distributed,then
Q23: The proportion of the total budget allocated
Q24: In establishing the project's baseline,the time-phased budget
Q25: Establishing the project's baseline requires _.<br>A)the work
Q26: Find the area under the normal curve