If Project Completion Times Are Normally Distributed,then Which of the Following

Question 22

Multiple Choice

If project completion times are normally distributed,then which of the following statements is FALSE?


A) The due date of a project is to the left of the mean.
B) The mean of project completion times is in the middle of the distribution.
C) There is a 50% chance that the project will be completed before the mean of project completion times.
D) There is a 50% chance that the project will be completed after the mean of project completion times.