Multiple Choice
If project completion times are normally distributed,then which of the following statements is FALSE?
A) The due date of a project is to the left of the mean.
B) The mean of project completion times is in the middle of the distribution.
C) There is a 50% chance that the project will be completed before the mean of project completion times.
D) There is a 50% chance that the project will be completed after the mean of project completion times.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: A project's baseline represents _.<br>A)our best understanding
Q18: If the most optimistic time for completing
Q19: Find the area under the normal curve
Q20: The formula for the expected duration of
Q21: In calculating the time-cost trade-off combinations for
Q23: The proportion of the total budget allocated
Q24: In establishing the project's baseline,the time-phased budget
Q25: Establishing the project's baseline requires _.<br>A)the work
Q26: Find the area under the normal curve
Q27: If a project is expected to be