Multiple Choice
In line balancing,the desired cycle time (C) is given by ______.
A) (Daily production time available) / (Units to be produced daily)
B) (Daily production time available) / (Number of workstations available)
C) (Units to be produced daily) / (Daily production time available)
D) (Total time used) / (Units to be produced daily)
Correct Answer:

Verified
Correct Answer:
Verified
Q16: A service blueprint refers to _.<br>A)a tool
Q17: _ are sometimes called gozinto charts.<br>A)Assembly charts<br>B)Assembly
Q18: Which of the following is NOT a
Q19: A graphic used to analyze and design
Q20: Line balancing refers to _.<br>A)the organization of
Q22: Real-life layout problems can be solved _.<br>A)manually<br>B)graphically<br>C)using
Q23: Which of the following rules assigns tasks
Q24: If the sum of all task times
Q25: ABC Corporation would like to evaluate
Q26: Which of the following is NOT true