Multiple Choice
If the sum of all task times is 100 and the cycle time is 10,then ______.
A) the number of workstations is 10
B) the number of workstations is 1,000
C) the balance efficiency is .88
D) the idle time is 3
Correct Answer:

Verified
Correct Answer:
Verified