Multiple Choice
Within the project charter,the scope overview accomplishes all of the following EXCEPT:
A) identifies the major schedule milestones for the project
B) describes how the work will be done to meet the specified requirements.
C) states what is and is not included in the project, at a fairly high level.
D) describes what needs to be accomplished - all the characteristics that must be present in the project deliverables.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Which of the following statements accurately describes
Q24: The charter signing represents the transition from
Q25: Risks,assumptions and constraints are included in the
Q26: Which of these charter elements should persuade
Q27: Briefly discuss the importance of the project
Q29: The project business case provides a high-level
Q30: Which of the following charter elements defines
Q31: The signing of the project portfolio statement
Q32: A deliverable is a unique and verifiable
Q33: The project master network is a high-level