Multiple Choice
Which of these charter elements should persuade decision makers to support the project and inspire team members and key stakeholders to work hard toward successful completion of the project?
A) the project vision statement
B) the business case
C) the project motto
D) the team operating principles
Correct Answer:

Verified
Correct Answer:
Verified