Multiple Choice
The milestone schedule in the project charter:
A) is a schedule that provides detailed data for when each project activity should begin.
B) is a detailed schedule that shows the planned duration for every activity in the project.
C) is a high-level plan that indicates a few significant accomplishments anticipated over the life of the project.
D) is a summary-level schedule that shows how major project tasks are sequenced.
Correct Answer:

Verified
Correct Answer:
Verified