The Milestone Schedule in the Project Charter:​

Question 39

Multiple Choice

The milestone schedule in the project charter:​ 


A)  is a schedule that provides detailed data for when each project activity should begin. 
B)  is a detailed schedule that shows the planned duration for every activity in the project. 
C)  is a high-level plan that indicates a few significant accomplishments anticipated over the life of the project. 
D)  is a summary-level schedule that shows how major project tasks are sequenced.