Multiple Choice
Which of the following statements most accurately identifies the typical contents of the project charter?
A) requirements, specifications, test protocols and test results
B) statement of work, terms and conditions, clauses and delivery instructions
C) business case, milestone schedule, resource estimates and team operating principles
D) purpose, literature review, methodology, results and conclusions
Correct Answer:

Verified
Correct Answer:
Verified
Q10: Which section of the project charter publicly
Q11: The project charter serves all of the
Q12: A project charter can vary in its
Q13: A charter can be used to quickly
Q14: During iteration planning in an agile project,agreement
Q16: On agile projects the first iteration is
Q17: A project sponsor is wise not to
Q18: During project charter creation there is typically a
Q19: In contrast to a legal contract,the parties
Q20: A well-written business case should persuade decision-makers