Multiple Choice
A project sponsor is wise not to sign a project charter authorizing work until the project manager and team show that they have ____:
A) learned to work together well.
B) gathered requirements from key stakeholders.
C) reviewed lessons learned from recently completed projects in order to avoid similar mistakes.
D) prepared a comprehensive schedule and budget.