Multiple Choice
Which of the following statements accurately describes a communications management plan?
A) a formal document that describes how the project will be initiated and planned
B) a living document that considers stakeholders' information desires and guides the project communications.
C) a formal document that defines how the project will be terminated and closed
D) a formal document that focuses on how the project's financial results will be tracked
Correct Answer:

Verified
Correct Answer:
Verified
Q31: By identifying stakeholders and their needs,project managers
Q32: A stakeholder engagement matrix documents the engagement
Q33: Common purposes for project communications include status
Q34: Communications to stakeholders are necessary for which
Q35: A situation that requires a decision to
Q37: Which of these is<u> NOT</u> one of
Q38: Project managers should purposefully plan and carry
Q39: During stakeholder analysis,stakeholders can be prioritized based
Q40: A project communications plan generally includes all
Q41: Establishing a positive relationship with all key