Multiple Choice
Communications to stakeholders are necessary for which of the following reasons?
A) to help them take ownership of the project and make timely decisions
B) to keep them at arms length so progress can continue
C) to shift the burden of risk from the project team to the stakeholders
D) to provide input to team performance reviews
Correct Answer:

Verified
Correct Answer:
Verified