The stakeholder register information can be used to evaluate the interests of different stakeholder groups by performing a _______ analysis to identify where there may be common areas of interest between the groups.
A) MBWA (management-by-wandering-around)
B) ITSFWI (if-the-shoe-fits-wear-it)
C) WIIFT (what's-in-it-for-them)
D) PDCA (plan-do-check-act)
Correct Answer:

Verified
Correct Answer:
Verified