Multiple Choice
A _______ is the approved project plan mainly consisting of scope,schedule,and cost that is not normally altered unless a formal change control request is approved for modifying these plans.
A) requirement.
B) baseline.
C) benchmark.
D) component.
Correct Answer:

Verified
Correct Answer:
Verified