Multiple Choice
A _________ is a written request or formal proposal to propose changes to any project planning component such as a document,project deliverable,or baseline (scope,cost,and time) .
A) scope statement
B) change request
C) project charter
D) request for proposal (RFP)
Correct Answer:

Verified
Correct Answer:
Verified