Which of the Following Statements Correctly Describes the Critical Path?​

Question 15

Multiple Choice

Which of the following statements correctly describes the critical path?​ 


A)  The sequence of activities that represents the shortest path through the project network. 
B)  It determines the latest possible end date of the project. 
C)  It consists only of activities with zero float (slack) . 
D)  It consists only of activities with lag times