Multiple Choice
Figure 8-2 Software Programmer Loading Chart
-Consider the software programmer loading chart presented in Figure 8-2.What percent of available time is the software programmer assigned to work activities on Thursday?
A) 80 percent
B) 100 percent
C) 150 percent
D) 200 percent
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Critical chain project management is an alternate
Q12: Resource leveling is a network scheduling technique
Q13: Agile project schedules are limited to the
Q14: When resource overloads are extreme,project managers may
Q15: Estimate Activity Resources is the process of
Q17: Describe how crashing and fast tracking can
Q18: What is a responsibility assignment matrix (RAM)?
Q19: The components (principles)of Critical Chain Project Management
Q20: Critical Chain Project Management (CCPM)attempts to keep
Q21: What methods could a project manager use