The Components (Principles)of Critical Chain Project Management Include Which of the Following?
Multiple Choice
The components (principles) of Critical Chain Project Management include which of the following?
A) Estimate activity durations generously
B) Avoid multi-tasking.
C) Adhere strictly to completion deadlines - rather than finishing early or late.
D) Add a comfortable buffer to every project activity
Correct Answer:

Verified
Correct Answer:
Verified
Q14: When resource overloads are extreme,project managers may
Q15: Estimate Activity Resources is the process of
Q16: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-2 Software
Q17: Describe how crashing and fast tracking can
Q18: What is a responsibility assignment matrix (RAM)?
Q20: Critical Chain Project Management (CCPM)attempts to keep
Q21: What methods could a project manager use
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q23: When estimating resource needs,project teams should consider
Q24: When recruiting resources to support a project,it