Multiple Choice
Figure 8-1 RACI Chart
-Consider the RACI chart presented in Figure 8-1 (RACI stands for Responsible,Accountable,Consult,Inform) .Who is responsible for development of the specification?
A) the project manager
B) the project engineer
C) the contract officer
D) the data manager
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Project managers must often face the challenge
Q2: Even when a project team does not
Q3: If a project resource is excessively overloaded,it
Q5: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project
Q6: In order to avoid project delays,project managers
Q7: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q8: RACI (Responsible,Accountable,Consult,Inform)charts go beyond a communication plan
Q9: As the project manager identifies potential resources
Q10: When determining resource availability,project managers need only
Q11: Critical chain project management is an alternate