Multiple Choice
Figure 8-3 Programmers Resource Histogram
-Critical Chain method was developed to address several problems that are common in organizations that use traditional project scheduling.Which of the following describes a common problem addressed by the critical chain method?
A) Many team members render overly optimistic estimates of the time it will take them to complete project activities.
B) Many team members work solely on a single task until it is complete - impeding work on other related activities.
C) Many team members tend to use all of the time available for an activity rather than completing it early.
D) Many team members work best when multi-tasking
Correct Answer:

Verified
Correct Answer:
Verified
Q21: What methods could a project manager use
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q23: When estimating resource needs,project teams should consider
Q24: When recruiting resources to support a project,it
Q25: Crashing almost always accelerates the schedule while
Q27: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-1 RACI
Q28: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project
Q29: Which of these is NOT an issue
Q30: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-1 RACI
Q31: One approach to identifying which activities contribute