When estimating resource needs,project teams should consider all the following EXCEPT:
A) support needs such as information systems and other services.
B) the time required to communicate between activities.
C) issues involved in securing specific knowledge or skills that are required.
D) strengths and weaknesses of scoring models.
Correct Answer:

Verified
Correct Answer:
Verified
Q18: What is a responsibility assignment matrix (RAM)?
Q19: The components (principles)of Critical Chain Project Management
Q20: Critical Chain Project Management (CCPM)attempts to keep
Q21: What methods could a project manager use
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q24: When recruiting resources to support a project,it
Q25: Crashing almost always accelerates the schedule while
Q26: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q27: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-1 RACI
Q28: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project