Multiple Choice
Which estimating technique uses a statistical relationship between historical data and other variables (e.g.,square footage in construction,lines of code in software development) to calculate an estimate for scope,cost and duration?
A) analogous estimating
B) parametric estimating
C) bottom-up estimating
D) Monte Carlo estimating
Correct Answer:

Verified
Correct Answer:
Verified