Question 16

Multiple Choice

The _________is the approved budget,usually in a time distribution format,that is used to estimate,monitor,and control the overall cost performance of the project.


A)  management baseline. 
B)  cost baseline. 
C)  cost benchmark 
D)  control account

Correct Answer: